The MTBE project in Algeria, which was contracted by the company, successfully hoisted the first batch of 5 sets of equipment on August 13, successfully achieving the first hoisting milestone.
The carbon steel reactors delivered included 5 pieces of equipment including 2100-R-001A/B and 4100-R-001, which were the first batch of equipment delivered to the site for the MTBE project. To ensure the smooth progress of the first hoisting of on-site equipment installation, the MTBE project department organized multiple technical disclosures to clarify the division of responsibilities. The project coordination team, procurement quality inspection team, and construction management team performed their respective duties and worked closely together. Five carbon steel reactors completed the acceptance and installation within one week, successfully achieving the first important milestone in on-site equipment installation.