首页 >> EN >> News >> News
1# 200,000 nm3/h Natural Gas to Hydrogen Plant in Phase II Project of Zhejiang Petrochemical Co., Ltd. Put into Operation

On May 24, 1# 200,000 nm3/h Natural Gas to Hydrogen Plant in Phase II of the 40 MTA Refining and Chemical Project of Zhejiang Petrochemical Co., Ltd., with design made by the Company, was smoothly put into operation to produce on-spec hydrogen, all process indicators were normal in operation, and wastewater and gaseous waste was discharged to standard. Recently, Zhejiang Petrochemical sent a letter to the Company to express their thanks to the leaders, experts and engineering designers participating in the work of the project.

As informed, the design work of the project was started in May 2021.


信息来源: 
2023-06-01